DMSTA Simulation Results   Case: ISTOK_2   Period: 1/1/1989 to 12/31/2002          
                               
Case: Lake Istokpoga - B&M; revised outflow concs        
         
         
                               
Input Series   ISTOK_REV     Tanks in Series   2.0 Surface Area (km2) 112.0541          
Simulation Period 01/04/80 thru 12/31/02 Mean Water Load  (cm/d) 1.1 Mean Depth (cm) 158          
Output Period   01/01/89 thru 12/31/02 Max Water Load (cm/d) 11.4 Max Depth (cm)   210          
Calib Period   01/01/90   12/31/02 Inflow Conc  (ppb) 116.4 Freq Depth <  5 cm 0.0%          
Startup Interval (days) 3650 Iterations -9 Inflow P Load (mg/m2-yr) 365 Load Reduction   65%          
Avg Interval (days) 90 Wtr Bal Error 0.0% Outflow FWM  Conc (ppb) 46.6 Conc Reduction   60%          
Parameter Set:     none Mass B Error 0.0% Outflow C with Bypass 46.6 Time Freq Conc > 10 ppb 77%          
K (m/yr)   5.815 Kd (m/yr) 0 95th Percentile (ppb) 61.8 K - SS, C*=4 ppb (m/yr) 4.7          
C1 (ppb)   150.0 Weir Depth (cm) 150 Outflow Geo. Mean (ppb) 39.3 Storage Turnover (1/yr) 12.0          
C0  (ppb)   4.0 Cont Depth (cm) 0 Outflow GM,  Q>0 (ppb) 40.5 Mean Stored P (mg/m2) 325          
C2 (ppb)   0 Qout Intercept 2.0 Seepage Loss   0% Storage Inc/Net Removal 2%          
Zx  (cm)   40 Qout Exponent 1.5 HRT (days)   208.0 Outfl. Seepage (cm/d/cm) 0          
                               
 
                             
                               
                               
                               
                               
                               
                               
                               
                               
                               
                               
                               
                               
                               
                               
                               
                               
                               
                               
                               
                               
                               
 
                             
                               
                               
                               
                               
                               
                               
                               
                               
                               
                               
                               
                               
                               
                               
                               
                               
                               
                               
                               
                               
                               
                               
                               
                               
                               
                               
                               
                               
                               
                               
                               
                               
                               
                               
                               
                               
                               
                               
                               
                               
                               
                               
                               
                               
                               
Obs Load2 = Predicted Flow x Observed Conc                        
Green lines on x axis of concentration plots indicate model calibration period.  Statistics at top of sheet are for entire output period.            
03/02/05