DMSTA Simulation Results Case: SAV_Shallow Period: 07/20/98 to 11/06/00
Case: SAV Shallow (40 cm) Mesocosm  NATT site - SAV; Fixed Depth (40 cm) then  Variable (10-80 cm); biomass harvested in nov 199, then returned to tank
Input Series sav_z40 Tanks in Series 1.3 Surface Area (km2) 0.0000
Simulation Period 07/20/98 thru 11/06/00 Mean Water Load  (cm/d) 10.3 Bypass Volume 0.0%
Output Period 07/20/98 thru 11/06/00 Max Water Load (cm/d) 10.0 Mean Depth (cm) 42
Startup Interval (days) 621 Iterations 1 Inflow Conc  (ppb) 112.3 Max Depth (cm) 80
Avg Interval (days) 7 Inflow P Load (mg/m2-yr) 3535 Freq Depth <  5 cm 0.0%
Parameter Set:   none Outflow FWM  Conc (ppb) 37.4 Load Reduction 67%
K  (m/yr) 90.67 Sm (mg/m2)  0 Outflow C with Bypass 37.4 Time Freq Conc > 10 ppb 100%
C1 (ppb) 22.0 Sp (mg/m2) 0 95th Percentile (ppb) 47.9 Vol Freq Conc > 10 ppb 100%
C0  (ppb) 4.0 Qout Intercept 0.0 Outflow Geo. Mean (ppb) 35.4 Storage Turnover (1/yr) 13.4
Zx  (cm) 60 Qout Exponent 0.0 Outflow GM,  Q>0 (ppb) 35.4 Mean Stored P (mg/m2) 1394
Wtr Bal Error 0.0% Knet-Plug Flow (m/yr) 40.4 Storage Inc/Net Removal 18%
Mass B Error 0.0% Knet-NCSTR (m/yr) 64.0 Outfl. Seepage (cm/d/cm) 0
Calibration  Statistics for Period: 04/01/00 thru 11/06/00 Mean Mean
Count Observed Predicted Residual Resid% RSE% R2
Mean Depth (cm) 32 48.4 48.4 0.0 0% 1% 100%
Flow (cm/day) 0 #N/A #N/A #N/A #N/A #N/A #N/A
Flow-Wtd-Mean Conc (ppb) 32 43.3 46.5 -3.2 -7%
Geometric Mean Conc (ppb) 32 40.2 41.2 -1.0 -2% 39% 0%
Mean Conc (ppb) 32 42.5 45.9 -3.4 -7% 51% 0%
Outflow Load (mg/m2-d) 0 #N/A #N/A #N/A #N/A #N/A #N/A
Pred Q x Conc (mg/m2-d) 32 4.26 4.58 -0.32 -7% 51% 0%
 
 
Obs Load2 = Predicted Flow x Obs Conc
Green lines on x axis of concentration plots indicate model calibration period.
06/07/02